Current Status of the project
- Infrastructures works:
- Road works : Road construction works 100 % completed. Block topping works shall be taken up after completion of project main works.
- Staff Colony: 1 BKH & 2 BHK works are in full swing and final stage of construction.
- Dam Complex:
- Dam : 100 % excavation and concreting completed. Miscellaneous works like parapet wall, supporting works are in progress.
- Drift & Keywall : 100 % construction completed.
- Dam Left bank Protection works are in final stage.
- Head Race Tunnel
- 4.95 KM excavation and lining works completed.
- All adits plugging completed.
- Surge Shaft
- Excavation & Concreting completed
- Pressure Shaft:
- Excavation and lining works completed
- Power House
- Excavation & Concreting works completed in all respects
- Electro-Mechanical Works
- All equipment’s including BoP items are erected and commissioned
- Project Commissioning activities
- Reservoir filled up to MDDL level
- Water conductor system filled and tested
- Both machines spin test competed.
- Unit # 1 synchronized with grid on 05 May 2012.
- Unit # 2 synchronized with grid on 09 May 2012.
|