CURRENT STATUS

Current Status of the project

  • Infrastructures works:
    • Road works : Road construction works 100 % completed. Block topping works shall be taken up after completion of project main works.
    • Staff Colony: 1 BKH & 2 BHK works are in full swing and final stage of construction.
  • Dam Complex:
    • Dam : 100 % excavation and concreting completed. Miscellaneous works like parapet wall, supporting works are in progress.
    • Drift & Keywall : 100 % construction completed.
    • Dam Left bank Protection works are in final stage.
  • Head Race Tunnel
    • 4.95 KM excavation and lining works completed.
    • All adits plugging completed.
  • Surge Shaft
    • Excavation & Concreting completed
  • Pressure Shaft:
    • Excavation and lining works completed
  • Power House
    • Excavation & Concreting works completed in all respects
  • Electro-Mechanical Works
    • All equipment’s including BoP items are erected and commissioned
  • Project Commissioning activities 
    • Reservoir filled up to MDDL level
    • Water conductor system filled and tested
    • Both machines spin test competed.
    • Unit # 1 synchronized with grid on 05 May 2012.
    • Unit # 2 synchronized with grid on 09 May 2012.